Energy Department Confronts Fresh Legal Restrictions on Emergency Power for the Grid

Why It Matters

Recently, a U.S. Court of Appeals ruling has vacated a Department of Energy (DOE) order to delay the retirement of a Michigan coal plant. This decision calls into question the Trump administration’s use of Section 202(c) of the Federal Power Act, which dates back to 1935. According to a report from the Congressional Research Service (CRS), the court emphasized that the DOE’s authority is limited to addressing immediate grid-reliability risks, ruling that planned retirements do not fall under this purview.

The ruling impacts similar orders issued by DOE for plants across various states, including Pennsylvania, Washington, and Florida, where the relevant grid operators did not request such interventions.

Legislative Developments

Pending legislation proposes different approaches to this authority. The Senate bill (S. 4337) seeks to restrict retirement delays to emergencies that cannot be addressed otherwise and only upon request from grid operators. The House bill (H.R. 7977) aims to limit the authority to existing emergencies or those anticipated within six months.

The Big Picture

Section 202(c) grants the Secretary of Energy broad authority during emergencies affecting electricity generation, transmission, or delivery. This authority was passed to DOE in 1977 when it was established. A 2015 amendment allows emergency orders to override environmental requirements temporarily, but with certain constraints, including a maximum duration of 90 days and minimal adverse environmental impacts.

An Executive Order signed in April 2025 directed DOE to use legal mechanisms, including Section 202(c), to retain essential generation resources for regional reliability. However, the order lacks specificity regarding the duration of such powers.

In a July 2025 resource adequacy report, DOE projected a significant increase in electricity demand, emphasizing the need for additional generation and transmission capacity, regardless of whether grid operators would allow outages.

The Bottom Line

The CRS report highlights several points that Congress may want to consider: the duration of emergency orders, the definition and scope of what constitutes an “emergency,” and how these orders align with prudent utility planning principles. Historically, DOE has claimed that its emergency regulations are not substitutes for long-term planning by utilities.