Weston Business 51 Reconstruction Update
-
Current Schedule: The reconstruction of Business 51 through Weston is now anticipated for 2030-2031, a delay from the initial plans.
-
Pedestrian Safety Concerns: Weston is advocating for a pedestrian crossing at Neupert Avenue. The Wisconsin Department of Transportation (DOT) says the highway lacks the necessary space for this crossing due to a narrow median.
-
Existing Conditions: There is no dedicated crossing on Business 51 between Jelinek Avenue and Schofield Avenue, which poses safety risks for pedestrians.
-
DOT’s Position: The DOT has cited traffic volume and median width as reasons against a crossing, suggesting alternatives that may involve significant costs for the village.
-
Funding Challenges: Weston recently lost an opportunity for state funding for another pedestrian crossing project near the elementary school, further complicating safety initiatives in the area.
-
Future Steps: The village plans to continue discussions with the DOT and may consider covering costs for modifications to address pedestrian safety.
This update emphasizes the ongoing efforts of the village to enhance safety despite challenges posed by funding and DOT regulations.