PA Environment Digest Blog: DEP Inviting Energy Generation and Storage Proposals for 2027 PJM Fast-Track Interconnection Program Evaluations

Key Information

Response Deadline:

  • November 16

Project Requirements

  1. Minimum Accredited UCAP:

    • At least 250 megawatts.
  2. Commercial Operation Timeline:

    • Ability to achieve operation within 3 years of EIT submission (post-2027 window).
  3. Site Control:

    • Must obtain 100% site control for the proposed facility, interconnection facility, and switchyard by submission date.
  4. Project Types:

    • Both energy generation and storage projects must meet PJM’s proposed requirements.

Recent Developments

2026 Projects Announced

  • PJM Interconnection accepted three projects (as of October 8):
    • ENGIE IR Holdings LLC: Wayne 345 kV storage project in Crawford, PA, with 860 MW capacity.
    • Hunterstown: Natural gas facility upgrade in Adams, PA, adding 455 MW capacity.

2027 Round


Related Articles

  • Protests against data centers.
  • PUC Chairman’s commentary on electric generation facilities.
  • Battery storage legislation advancements.
  • Renewable energy development news.

For more detailed articles and updates, refer to the provided links in each section.